Two ChargePoint Express power cabinets at a Faith Energy DC fast charging site

Fleet Electrification · Trucks

Class 8 trucks charge at megawatts. The depot is an electrical project first.

An 18-wheeler carries a 400–1,000 kWh battery and expects it refilled overnight, or in under an hour on route. That is a 1 to 10 megawatt interconnection, medium-voltage switchgear on a 52–80 week lead time, and a civil scope the size of a small substation. Faith Energy self-performs that work for fleets, depot developers, and the operators who run charging hubs.

1.2 MWper port delivered by deployed Megawatt Charging System (MCS) hardware
400–1,000 kWhClass 8 battery pack across current models
2–2.5 kWh/mienergy a loaded Class 8 truck uses — 300–500 kWh a day on regional haul
52–80 wksmedium-voltage switchgear lead time — procurement sequencing is the schedule

What the Truck Needs

Class 6, 7, and 8 are different electrical problems.

Gross vehicle weight rating decides the battery, the battery decides the daily energy, and the dwell window decides the power. Design from those three numbers and the depot stops being a guess.

Class (GVWR)Typical vehiclesTypical batteryDepot charging we specify
Class 6 (19,501–26,000 lb)Box trucks, beverage, utility bodies150–250 kWhLevel 2 19.2 kW or DC 50–100 kW overnight, managed
Class 7 (26,001–33,000 lb)Straight trucks, refuse, Type D buses200–350 kWhDC 60–150 kW overnight, shared cabinets
Class 8 (33,001 lb and up)Tractors, drayage, regional and long haul400–1,000 kWhDC 150–350 kW CCS overnight; MCS up to 1.2 MW for on-route and mid-shift
Yard and terminal tractorsPort, intermodal, distribution yards100–250 kWhDC 50–150 kW opportunity charging between shifts

Planning-level ranges across current manufacturers. Final sizing comes from your telematics, route sheets, and the trucks on order.

The Depot Math

Twenty Class 8 trucks is 8 MWh a night. How you deliver it decides the utility bill and the schedule.

Everything at once

Twenty trucks plugged in at 350 kW is a 7 MW peak. That is a new utility service, a dedicated substation feed in many territories, and a 12–36 month interconnection before the first truck charges. Few depots need it, and the demand charges never stop.

Managed overnight

The same twenty trucks need about 400 kWh each over a 10-hour window: 800 kW average. Managed charging sequences them to be ready by departure, cabinets share power across positions, and the site fits a 1–1.5 MW service that many industrial parcels can get in a fraction of the time.

Buffered with storage

A battery energy storage system lets DC fast positions deliver peak power on a service that cannot carry it, then recharges off-peak. It is how a depot opens before the utility upgrade lands and how it avoids demand charges after. We size it from the same dwell data.

Built for the end state

Phase one energizes what today’s trucks need. The medium-voltage gear, duct bank, pads, and canopy structure are sized for the full fleet and for MCS positions, because adding them later means saw-cutting an operating yard. Procurement starts at contract signing against engineered one-lines.

Charging Hubs

We also build the hubs that fleets charge at on route.

Shared truck charging hubs at 5–10 MW with CCS and MCS positions, gated access, and canopies are being developed near freight corridors and intermodal yards by charging operators and property owners. The electrical infrastructure is 70–90% of what those hubs cost, and it is the same scope as a private depot at larger scale: the interconnection, the medium-voltage switchgear and transformers, the duct bank, the power cabinets, the lighting, and the commissioning. Faith Energy performs that work for hub operators and for investors building a charging network, and we service the equipment afterward across brands.

Investor and operator partnerships

Hardware we specify for truck depots and hubs.

From the brands we are an authorized reseller and certified installer for. We pair power cabinets, dispensers, storage, and software to the dwell data rather than to a logo.

Straight Answers

Truck depot charging, answered plainly.

What is Megawatt Charging (MCS), and does my depot need it?
MCS is the heavy-duty connector standard (SAE J3271) that moves charging beyond the CCS ceiling: deployed hardware delivers about 1.2 MW per port today, and the standard allows more. A depot needs MCS when trucks must turn around mid-shift in under an hour, which is on-route, drayage, and regional-haul work. Overnight depot charging of the same trucks works on CCS at 150–350 kW because the dwell window does the work. Most depots we design are CCS positions with conduit and gear sized so MCS positions can be added.
How many Class 8 trucks can charge on a 3 MW service?
Depends on the dwell window. A Class 8 regional-haul truck uses roughly 300–500 kWh a day. Over a 10-hour overnight window that averages 30–50 kW per truck, so a 3 MW service supports 40–60 trucks with managed charging. The same 3 MW supports only eight trucks charging simultaneously at 350 kW. Managed charging and power sharing are what make depot economics work; sizing the service for everything at full power is the most common error we correct.
Can a truck depot open before the utility service upgrade is finished?
Often, in phases. The first trucks can charge on the existing service with managed charging, a battery energy storage system can buffer DC fast charging on a service that cannot carry the peak, and battery-backed mobile DC chargers can cover a yard with no utility work at all. Those are bridges, not the end state. The utility application still has to be filed first because a new multi-megawatt service commonly takes 12–36 months.
What is the difference between depot charging and on-route charging?
Depot charging happens where the truck parks overnight, at moderate power, inside a long dwell window, on infrastructure the fleet or its depot partner owns. On-route charging happens at a public or shared hub during the shift, at the highest power available (up to MCS), paid per kWh. Most fleets need both: a depot for the base load and access to hubs for exceptions and longer routes. We build depots for fleets and hubs for the operators who run them.
What does a heavy-duty DC charging position cost?
Installed heavy-duty DC positions commonly run $60,000–$150,000 or more each, with multi-position sites sharing power cabinets and gear to improve the per-position number. Utility service work, when it is required, adds $50,000–$500,000 or more and months of lead time. Our depot cost guide breaks the ranges down by operating profile.
What about yard tractors, drayage, and refuse trucks?
They are the easiest heavy-duty cases to electrify because the routes are short, repetitive, and return to the same yard. Terminal tractors and refuse trucks usually charge overnight on CCS at 50–150 kW with no on-route charging. Drayage is the exception: short dwell at the port and long queue times push some operators toward on-route charging and higher-power positions.
Who operates the depot after commissioning?
Either your fleet team with our training and documentation, or Faith Energy under a service agreement with 24/7 monitoring, preventative maintenance, and repair across charger brands. Heavy-duty depots justify service contracts faster than any other site type because a down position is a parked truck and a missed load.

Next Step

Trucks on order? Start with the power question.

Send us the truck list, the routes, and the parcel. Our engineers return the capacity screen, the utility path, the gear sequencing, and a depot design phased to your delivery schedule.

Email usStart project review