An 18-wheeler carries a 400–1,000 kWh battery and expects it refilled overnight, or in under an hour on route. That is a 1 to 10 megawatt interconnection, medium-voltage switchgear on a 52–80 week lead time, and a civil scope the size of a small substation. Faith Energy self-performs that work for fleets, depot developers, and the operators who run charging hubs.
What the Truck Needs
Gross vehicle weight rating decides the battery, the battery decides the daily energy, and the dwell window decides the power. Design from those three numbers and the depot stops being a guess.
| Class (GVWR) | Typical vehicles | Typical battery | Depot charging we specify |
|---|---|---|---|
| Class 6 (19,501–26,000 lb) | Box trucks, beverage, utility bodies | 150–250 kWh | Level 2 19.2 kW or DC 50–100 kW overnight, managed |
| Class 7 (26,001–33,000 lb) | Straight trucks, refuse, Type D buses | 200–350 kWh | DC 60–150 kW overnight, shared cabinets |
| Class 8 (33,001 lb and up) | Tractors, drayage, regional and long haul | 400–1,000 kWh | DC 150–350 kW CCS overnight; MCS up to 1.2 MW for on-route and mid-shift |
| Yard and terminal tractors | Port, intermodal, distribution yards | 100–250 kWh | DC 50–150 kW opportunity charging between shifts |
Planning-level ranges across current manufacturers. Final sizing comes from your telematics, route sheets, and the trucks on order.
The Depot Math
Twenty trucks plugged in at 350 kW is a 7 MW peak. That is a new utility service, a dedicated substation feed in many territories, and a 12–36 month interconnection before the first truck charges. Few depots need it, and the demand charges never stop.
The same twenty trucks need about 400 kWh each over a 10-hour window: 800 kW average. Managed charging sequences them to be ready by departure, cabinets share power across positions, and the site fits a 1–1.5 MW service that many industrial parcels can get in a fraction of the time.
A battery energy storage system lets DC fast positions deliver peak power on a service that cannot carry it, then recharges off-peak. It is how a depot opens before the utility upgrade lands and how it avoids demand charges after. We size it from the same dwell data.
Phase one energizes what today’s trucks need. The medium-voltage gear, duct bank, pads, and canopy structure are sized for the full fleet and for MCS positions, because adding them later means saw-cutting an operating yard. Procurement starts at contract signing against engineered one-lines.
Charging Hubs
Shared truck charging hubs at 5–10 MW with CCS and MCS positions, gated access, and canopies are being developed near freight corridors and intermodal yards by charging operators and property owners. The electrical infrastructure is 70–90% of what those hubs cost, and it is the same scope as a private depot at larger scale: the interconnection, the medium-voltage switchgear and transformers, the duct bank, the power cabinets, the lighting, and the commissioning. Faith Energy performs that work for hub operators and for investors building a charging network, and we service the equipment afterward across brands.
Investor and operator partnershipsFrom the brands we are an authorized reseller and certified installer for. We pair power cabinets, dispensers, storage, and software to the dwell data rather than to a logo.
Straight Answers
Next Step
Send us the truck list, the routes, and the parcel. Our engineers return the capacity screen, the utility path, the gear sequencing, and a depot design phased to your delivery schedule.